Type
Internal restructuring
Country
Bulgaria
Region
Yuzhna Bulgaria; Yugozapaden; Kyustendil
Location of affected unit(s)
Bobov Dol
Sector
Utilities
Electricity, Gas, Steam And Air Conditioning Supply
Electricity, Gas, Steam And Air Conditioning Supply
35.11 - Production of electricity

186 - 400 jobs
Number of planned job losses
Job loss
Announcement Date
16 July 2013
Employment effect (start)
16 August 2013
Foreseen end date
15 September 2013

Description

The consortium Energy MK JSC is to cut 186 jobs at its thermal power plant Bobov Dol in Bulgaria. According to the sources, the regional labour office in Doupnitsa was officially informed about the measure.

Apart from the job cuts, a 30% wage reduction is going to be implemented for the remaining staff. The job reduction plan is going to take place by mid September 2013.


Sources

  • 16 July 2013: Economic
  • 18 July 2013: Bulgariasega
  • 16 July 2013: dariknews

Citation

Eurofound (2013), Bobov Dol, Internal restructuring in Bulgaria, factsheet number 75675, European Restructuring Monitor. Dublin, https://restructuringeventsprod.azurewebsites.net/restructuring-events/detail/75675.